1. Put pumps in rows, not jobs

The question every dispatcher answers all day is "which pump is free at 7 a.m. tomorrow?". Rows per pump, with time running left to right, answer it at a glance. Jobs become bars on the pump's row. Keep a separate column for jobs that don't have a pump yet.

2. Take every request the same way

Phone requests get lost. Ask contractors for the same six things every time: site address, pour date and window, pour type, yards, the boom or line length they think they need, and a contact on site. A request link — or a printed form by the phone — keeps it consistent.

3. Match the pump to the pour, then confirm on site

Filter by type (boom, line, trailer) and listed reach first. A pump whose listed reach is at least the requested reach is a candidate, not a guarantee: setup position, obstacles and outrigger room decide what actually reaches. Always confirm reach and setup with the operator and the site.

4. Never double-book a pump or an operator

Before placing a bar, check both the pump row and the operator's other jobs. Back-to-back is fine when the first job's end time equals the next job's start time; an overlap is not. Software should block the overlap and tell you which job is in the way.

5. Give operators the day in their pocket

Operators should see only their jobs: address, window, pour type, yards and notes. They tap arrive, start, pour, finish and washout as it happens, enter yards and hose length, and get the customer's signature before leaving. On sites with no signal, the phone should keep everything and sync later.

6. Bill the same day

A signed ticket with times and yards is the invoice's evidence. Turn it into an invoice draft the same afternoon, export the day's tickets to your bookkeeping, and keep the PDF. Signed tickets shouldn't change — corrections are added as a revision with a reason.

7. Watch the hour meters

Record the pump's hour meter at the end of each job. When the hours since the last service pass the interval, flag the pump on the board before it gets booked for a big pour.

A day-of checklist

  1. By 3 p.m.: every request for tomorrow is accepted or declined.
  2. By 4 p.m.: every accepted job has a pump and operator; service-due pumps are off the board.
  3. Morning: operators open their job list; changes go on the board first, then to the operator.
  4. End of day: every finished job has a signed ticket; invoice drafts are created and exported.